Well #7 is . . . well . . . now pumping

With accommodations, new well is pumping water as of April 1

 

 

well 2
AS WATER DEPARTMENT employee Dave Watkins, front right, opens up the valve to the new line to the city’s existing well on the east side of Mountain Lake, as Water Department Supervisor Kevin Krahn, left, and Dan Cronnick of Thein Well Company of Spicer, center, stand by the new well.

 

 

well 3
JOINING KRAHN, LEFT and Cronnick, center, at the new well as it begins its pumping are joined by Mark Juker of Automatic Systems, right, the company that completed the programming for the operation of the new well.

 

 

 

No joke.

It appears that delays in completing the Well #7 project for the City of Mountain Lake are coming to an end. The new well, dug and built on the former Boldt’s Watercare property east of the lake, along with the connecting pipe that was bored to the city’s Well Meter Building, began pumping late Wednesday morning, April 1.

Currently, the water being pumped from the new well will be sent to the Water Treatment Plant, and, in combination with water from other city wells, be tested together for whatever necessary chemical treatment and RO (reverse osmosis) settings.

According to Andy Kehren, City Engineer and Senior Principal Project Manager for Bolton & Menk, it could be approximately one week until the well is actually running online.

Kehren added that, “As a condition of the Public Facilities Authority (PFA) loan, the federal American Iron and Steel rules apply to all materials furnished for the project. American-manufactured iron and steel products have been available for all of the project components – except the check valve. After exhausting all avenues to find an American-made check valve, about four months ago the contractor special-ordered a check valve that will conform to the American Iron and Steel requirements. At this time the check valve has not yet been received by the contractor.

“The check valve is required to complete the work. However, during this interim period, the contractor installed a spool in the location that the check valve will ultimately be placed. The spool installation – and the balance of the required piping modifications in the Well Meter Building – were completed over the first days of this week. Automatic Systems was on-site on  Monday, March 30, Tuesday, March 31 and Wednesday, April 1 to complete the programming required to operate the new well.

“Until the check valve arrives and is installed, the foot valve that was installed above the pump in Well #7 for backflow prevention will be relied on. If a problem arises using the foot valve for backflow prevention, other alternatives will be considered.”

History of the City of Mountain Lake’s newest well – Well #7

The digging of the City of Mountain Lake’s newest well began on Tuesday, September 2, 2014. The well was dug on the former Boldt’s Watercare property site at the north intersection of Nickel Street and 10th Street North, adjacent to Cottonwood County Road #9. To reach the current Well Meter Building, located in the southwest corner of Mountain Lake City Cemetery, a new raw water line was bored under 10th Street North, and followed 9th Street to the building location.

The digging of this new well was a top Utility Commission priority. Earlier attempts to locate a suitable source of water on city property ended up unsuccessful. In 2013, the Utility purchased the former Boldt’s Watercare after test boring proved there was water on the property.

This project was bumped up to urgent when production at two of the city’s wells dropped in January 2014.

GM Contracting of Lake Crystal is the general contractor, while subcontractors for the project are Thein Well Company of Spicer, Kuehl Electric of St. James and MR Paving of New Ulm. GM Contracting was the lone bidder on the project, coming in at $723,257.23 – or 30% above the engineer’s estimate. A change order in the project, however, reduced the bid amount by $58,775.15. This reduction was due to the contractor opting to use horizontal directional boring, which is less costly than an open trench and means less traffic control costs. The bid amount was further reduced by having city staff – and not the contractor – complete the tree removal necessary for the project.

The digging of the well was completed in the fall, but was not operational until all electrical, computer technology and other related work was finalized.

Funding for the well tied to housing rehabilitation

The city received a  2014 Department of Employment and Economic Development (DEED) Small Cities Development Program (SCDP) grant which will be teamed with an 80% grant/20% loan from Public Facilities Authority (PFA)  and a $100,000 contribution from the Mountain Lake Economic Development Authority (EDA) – to build the new well, dig a raw water line from the property to the Water Meter Building to close several old, low-producing well (including in the Mountain Lake Fire Hall) – as well as for the rehabilitation of approximately 20 owner-occupied homes. Only $47,532 will need to be repaid to the PFA.

The SCDP grant was also for the rehabilitation of approximately 20 owner-occupied houses. Rehab activities will include correcting structural deficiencies and code violations, improving energy efficiency, health and safety concerns and accessibility. Additionally, homes will be tested for lead paint, mold, radon and asbestos.

The grant provides 80% of each project’s cost. The remaining 20% will be drawn from a variety of sources, including owner funds, bank financing, Minnesota Housing Finance Agency (MHFA) funds, weatherization, Energy-Related Repair funds and Lead Hazard Control grants.

These SCDP funds will be secured with a 10-year 0% interest deferred loan. All of the loan will be repaid if the client sells the home within the first year. Thereafter, a reduction of 10% per year will be applied to the payback amount until  10 years have passed, whereupon the loan is forgiven.

The target area for housing – the western half of the city – was selected because a large number of those returning the Fall 2013 SCDP questionnaire were low-to-moderate income homeowners living that part of the city. Priority will be given to homeowners in the target area who indicated an interest in housing rehab.

 

Facebook Comments